March
2009 | Dave Druker, 10th
Street
The
figure of $2.5 million
has been bandied about
as the cost of the Garden
Del Mar project to go
through Del Mar’s
Prop B process. While
it did cost the owners
of this project $2.5
million, most of the
costs were not due to
Prop B but due to the
size, scope of the project
and the need for a redesign.


If
there was no Prop B.
how would the Garden
Del Mar project have
been approved? Because
the project was larger
than the allowed FAR,
the owners would have
had to create a specific
plan. This specific
plan would have required
an environment impact
report and a development
agreement. The specific
plan would have required
Planning Commission,
Design Review Board
and City Council review.
There would probably
have been many more
meetings than the two
Planning Commission,
two DRB and three City
Council meetings that
occurred in the most
recent approval cycle.
But
there was a Prop B and
there were added costs
for this process. Were
these costs because
of the process or the
way the council and
the developer decided
to go through the process?
For example, part of
the cost was the redesign
of the project. If the
developers had not redesigned
the project, would it
have received an 85%
approval at the ballot?
Also by not initially
listening to the feedback
from the community about
the design, the developers
prolonged the process
of approval.
If
the council had not
set up a citizen advisory
board to address the
numerous project issues,
the developers would
have had to meet with
the neighbors and create
appropriate mitigation
for the project. Instead
of paying for attendance
at the meetings, the
developers would probably
have had to spend money
on a campaign to assuage
the voters that the
Garden Del Mar project
was correct for the
neighborhood. Who knows
what the cost of the
campaign would have
been if there was an
organized opposition
to the project.
If
there was no Prop B,
then the developers
would not have had to
spend money on exceptional
benefit. In the grand
scheme of things, the
direct contribution
to the community for
exceptional benefit
is a small portion of
the project. Ultimately,
the developers and the
Prop B process gave
us a project that a
vast majority of Del
Mar is happy about and
that is priceless.
| f in
pdf form. Click here |
|
|